17 July 2014

La Romaine: on or off? #nlpoli

On Monday,  Quebec premier Philippe Couillard left the impression that the third and fourth dams on the La Romaine river were in doubt. 

Couillard told reporters as he headed to the meeting of New England Governors and Eastern Canadian Premiers that Hydro-Quebec would finish the first two dams, currently under construction, and then make a decision:

“We will evaluate them and we will see exactly what is needed. [translation of “On va les évaluer et on va voir justement quel est le besoin.”

According to La Presse, Couillard said that HQ would assess electricity needs for industrial use within Quebec as well as for export before determining whether to build the last two dams of a four dam project.

A report commissioned for the short-lived Parti Quebecois administration last year concluded that continued development of La Romaine would not be profitable,  given the large surplus of electricity currently available to Hydro-Quebec.

The entire cost of the the La Romaine development is pegged at $6.5 billion for approximately 1500 megawatts of electricity.  If HQ proceeds with the remaining dams, the current schedule will see the third on line by 2017 and the fourth producing electricity by 2020.

A statement issued by Couillard’s office on Tuesday changed the story.  The statement said that planning was already underway for the third and fourth dams.  It also repeated Couillard’s comment from Monday that the surplus generating capacity would be an asset for Hydro-Quebec in the marketplace.

-srbp-

02 June 2010

Lower Churchill costs: now up to $14 billion and counting

According to Premier Danny Williams, the Lower Churchill project – which he estimates at a cost of up to $12 billion -  is “ the lowest cost , the cheapest hydroelectric project in all of North America.”  Dead link to CBC story June 1, 2010 quoting Williams]

That’s more than a bit of a stretch, even for the Old Man and his legendary love of absurd comments bordering on the ridiculous.

A simple comparison of costs based on information in the public domain demonstrates that the Premier’s claims in this case are once again nothing short of ridiculous.

For example, a 1998 cost estimate of the project elements to develop both Lower Churchill dam sites and the transmission infeeds (one to Quebec and the other to Soldier’s Pond, just west of St. John’s) put the cost at $10.5 billion.

Now we can add to that the costs of getting the power across to Nova Scotia, for example and then down into the United States.

According to the Chronicle-Herald, a study done for the Nova Scotia government put the cost of connecting from Newfoundland to Cape Breton between $800 million and $1.2 billion.  Hooking to the US would add another $2.0 billion to $3.0 billion to that.

The only thing we’d be missing at that point is a connection from Deer Lake to Port aux Basques or where ever the line would go to connect with Nova Scotia.

Even at that, we’d be looking at between $2.8 billion to $4.2 billion on top of the $10.5 billion to use the so-called Atlantic route.

That puts the grand total at between $13.3 billion and $14.7 billion.

Not bad for a project that the current administration touted in 2005 as costing about $3.3 billion.
But since Danny Williams said it is the lowest cost hydro-project in North America we can be pretty much assured he was talking through his hat.

Maybe he was talking in relative terms, like say as a measure of how much it would cost to get the power up and out to market for every megawatt produced;  it’s called, not surprisingly, a cost per megawatt calculation.

Well, the Lower Churchill’s 2800 megawatt project would come out as follows.  For good measure, there’s a comparison with the La Romaine project in Quebec which is already under way.

Cost
Cost per megawatt
Notes

$10.5 billion

$3.75 million

1998 projected cost, includes connection Quebec and Newfoundland only (currently under enviro assessment)

$12.0 billion

$4.285 million
2010 Williams upper-end estimate of project costs, link to Newfoundland and Quebec only. [Update]

$13.3 billion

$4.75 million

Low-end estimate to connect to NS and US

$14.7 billion

$5.25 million

High-end estimate to connect to NS and US

$6.5 billion

$4.195348 million

Hydro-Quebec’s La Romaine, 1550 MW

British Columbia’s Site C dam will deliver 900 megawatts for an estimated $6.0 billion so that will more expensive on a cost per megawatt basis.  That’s over $6.6 million per megawatt.  Another power project in Ontario will add 440 megawatts of power to an existing hydro structure for a cost of $2.0 billion or $4.5 million per megawatt.

By comparison, wind power projects run about $3.5 million per installed megawatt, according to a wind industry website.

-srbp-

07 March 2009

Romaine clears environmental review

The Romaine hydro project in Quebec cleared the joint federal-provincial environmental review panel on Friday.

In making its decision, the panel noted that it worked within the legal boundary between Quebec and Newfoundland and Labrador:

Par ailleurs, elle a évalué les effets environnementaux du projet selon le tracé de 1927 du Conseil
privé et ne se prononce aucunement sur la validité de cette frontière entre le Québec et Terre-Neuve-et-Labrador.

Quel shock for the League of Professional Victims.

For those whose French isn’t that good here’s a rough (not literal) translation:

In addition, it evaluated the environmental effects of the project according to the boundary set in 1927 by the Privy Council and does not come to a conclusion at all about the validity of this border between Quebec and Newfoundland and Labrador.

It comes to no conclusion since it had no grounds on which to question the whole issue. So much for the twaddle pushed by the League that somehow this decision would see the federal government endorse a border change. Apparently only one private individual appeared before the committee to recommend that the border be erased altogether.

There is extensive discussion of the environmental issues, including the potential impact on migratory caribou herds. The panel recommends that the Quebec ministries involved develop a plan with the Government of Newfoundland and Labrador to protect the caribou.

-srbp-